Blog Entry# 1476321
Posted: May 20 2015 (09:36)
148 Responses
Last Response: Jun 20 2018 (09:04)
148 Responses
Last Response: Jun 20 2018 (09:04)
Rewari Bhiwani Hisar Double and Electrification work Pic , eatrh work of Double line is 75-80% done upto Manheru and Poles are also reached at almost all station and upto Jharli
Pic taken on 15 May 2015
Pic taken on 15 May 2015
146 Posts
Ye sab jaldbaaji Mei work Krne kaa kaa hii result hai, tabhi pichlii baar CRS Hua tab Bahut saari mistakes thi.
Latest Update On Rewari-Manheru Section ...
Doubling Work - 80% completed bw Jharli to Manheru
Electrification Work completed almost 60% as poles have been erected on both lines .Installing of OHE equip and wiring work yet to be done
Picture Source: RF from Bhwani khera
Doubling Work - 80% completed bw Jharli to Manheru
Electrification Work completed almost 60% as poles have been erected on both lines .Installing of OHE equip and wiring work yet to be done
Picture Source: RF from Bhwani khera
Finnaly E loco start on ROK BNW section and 14085 is the first train which run with elco WAP7 on 25 May 2018 and reached Bhiwani , and next day GD also start running with E loco from BNW to GKP,
Finnaly E loco reached at Hisar Jn now let see when Eloco will be start on B/W Bhiwani and Rewari