Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt

RailCal app

site support

अपनी संपूर्ण क्रांति, राजधानी से कम है के 🔥- Arjun Rai

Search Forum
<<prev entry    next entry>>
Blog Entry# 1866955
Posted: May 27 2016 (18:19)

2 Responses
Last Response: May 27 2016 (22:43)
General Travel
2487 views
0

May 27 2016 (18:19)  
 
promethsuresh^~
promethsuresh^~   3536 blog posts
Entry# 1866955              
SBC- MYS electrification and doubling update?
Translate to English
Translate to Hindi

1 Public Posts - Fri May 27, 2016

1998 views
3

May 27 2016 (22:43)
swaroopghegde~
swaroopghegde~   638 blog posts
Re# 1866955-2              
Most and i mean most has been completed till mandya.
MYA - Y almost done
Y - as of today stable poles and caterers but no wiring
Y-BDRL completed except a 1.5km stretch (like a valley)
BDRL
...
more...
- chandagirikoppal s over
Chandagirikoppal to PANP only pits are done and in progress
PANP - ZERO
PANP - S - mixture of everything.
S- ZERO
S-NHY - almost done
NHY- ZERO
NHY-MNGT - nearing completion
Rest to mys is nil

Translate to English
Translate to Hindi
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy