SunilKulkarni~ 2006 blog postsBidar Gulbarga Railway line updates.
The Margutti Tunnel works achieved a major breakthrough
Tunnel boring completed, Both end connected on 3rd December... There is light at the end of tunnel ...
The Margutti Tunnel works achieved a major breakthrough
Tunnel boring completed, Both end connected on 3rd December... There is light at the end of tunnel ...
Thats great. The deadline was 15th Dec but railways managed to complete 12 days early.
Any new updates about the line sir? Will the promise of inauguration by March be kept?
Have they laid the rails in the full stretch ?? When is the CRS inspection for GR-Bidar line ??
not yet last time when i visited in Dec Rails were still not laid .. hopefully when I visit next time will get more details.