Updates on ET-JBP electrification as on 6/2/2017.
1. The work of ET-PPI is approximately 99% completed.the bagratawa bridge and tunnel is now fully under wires.i think by this pace of work at the end of this month we can see the elocos on ET-PPI section.
2. The work of electrification is started on NU-PPI section.the pole work is done til kareli and work of pole is going on kareli station.the work of hole is completed till gadarwara and work of digging hole is in progress from GAR-PPI.
1,2...
more...
1. The work of ET-PPI is approximately 99% completed.the bagratawa bridge and tunnel is now fully under wires.i think by this pace of work at the end of this month we can see the elocos on ET-PPI section.
2. The work of electrification is started on NU-PPI section.the pole work is done til kareli and work of pole is going on kareli station.the work of hole is completed till gadarwara and work of digging hole is in progress from GAR-PPI.