CR is saying work on doubling between Nagothane and Roha is progressing, it is not stalled. If it is true, does anybody know it's status.?
3 Posts
Nagothane-Nidi is doubled. I traveled via NH 66 just few days back and the railway over bridge that was mentioned is complete. It isn't commissioned yet, there was a yellow plasser van standing there when i passed by it.
Two megablocks were taken near Nidi, one one 28/02 for subway work and other one on 03/03 for cut & connection. Even when I enquired on Twitter, CR GM replied me that work is progressing. One reporter has mentioned that March is the deadline for Nagothane Roha section. I don't konw whether they are working on Nidi Roha section or not. But it seems they will open Nagothane Nidi first.
they should start it, it only requires a CRS inspection. Although since not much work is left on Roha-Nidi stretch, they may do the balance work left in Ashtami area and commission the entire stretch in one go.