Feb 21 2017 (17:26) 17230/Sabari Express (PT) | GNT/Guntur Junction (7 PFs)
Moulali Saheb G~
Moulali Saheb G~ 398 blog postsSabari Express with Ed Wap4 loco ready to leave pf1...
Gnt-Tel doubling with electrification status poles are erected almost entire route and some part is with ground levelling and poles
Gnt-Tel doubling with electrification status poles are erected almost entire route and some part is with ground levelling and poles
1 Public Posts - Fri Feb 24, 2017
The section is Guntur Guntakal doubling 403 km with 80-100km of track in forest section with chat route. It requires at least 3000-4000crs for and huge allocations every financial year for completion.So the time period is 2019.