Present doubling works going on between GY-Kallur jn , GtL-Kallur jn , ATP-DMM !
Gy- kalluru and Gy- dharmavaram Rites company handling this projects.currently they are handling ynk- pkd double line once they will complete they will look on gy -dmm section.Eenadu news published tenders are called and cancelled later they published Rites company will complete this project. Gtl to kalluru doubling and electrification handling Guntakal guage conversion department.
It is because 22691/2 has LSA with 22693/4. Only after 22693/4 finishes its run, 22691/2 will get eloco that is from July.
That is what I heard. Once 22693/22694 is discontinued, we can expect electric loco. If eloco is given now, the link plan has to be altered and the dloco has to idle at SC.