Feb 15 2018 (17:05) MLDT/Malda Town (7 PFs)
Rohit Kumar Kushwaha~
Rohit Kumar Kushwaha~ 115 blog postsEscalator is being installed in full pace at PF No. 1 in Malda Town Station.
1 Posts
Impossible from 25/02/2018. Railway is playing joke with General public no pole had been erected entirely at New Farakka Junction, Farakka Barrage and Malda Town Railway station.
Hole are being dug out from 08/02/2018 at New Farakka North end cabin and Malda Town station
You can watch match my videos on Youtube there are no sign of electrification work near New Farakka Jn.
Hole are being dug out from 08/02/2018 at New Farakka North end cabin and Malda Town station
You can watch match my videos on Youtube there are no sign of electrification work near New Farakka Jn.
And you here what they say .. energisation from 25.02.2018 ... How could it be possible without ohe n poles
Kiul- jmp already energized from dec17 even no wires at all...,,π ERπ
Is Energization notice dene ka reason kuch or ho sakta hai jisse hum samjh nai paa rahe
Actually they give energisation notification early to create general awernance within the public.
Katihar Malda Court Energisation notification was released on December 2016 with no Catenery installed at Malda Court Station but the section became electrified on December 2017.
Here the synerio is different as No pole has been erected and SSP at Kaltipur is not ready at all only boundary has been made.
Katihar Malda Court Energisation notification was released on December 2016 with no Catenery installed at Malda Court Station but the section became electrified on December 2017.
Here the synerio is different as No pole has been erected and SSP at Kaltipur is not ready at all only boundary has been made.