High rise #Electrification started on VG - GIMB .
Poles layed . Toward JHUND Jn.
Wiring done till some extent .of 2km approx .from VG onwards .
After that horizontal placing remaining on poles .
Zoom...
more...
Poles layed . Toward JHUND Jn.
Wiring done till some extent .of 2km approx .from VG onwards .
After that horizontal placing remaining on poles .
Zoom...
more...
4 Posts
Mahesana viramgam okha
Dhagndhra surendngar pipavav
Viramgram samkhiyali
Palanpur Samakhiyali gandhidham
Gandhidham kandla /mundra
Wankaner...
more...
Dhagndhra surendngar pipavav
Viramgram samkhiyali
Palanpur Samakhiyali gandhidham
Gandhidham kandla /mundra
Wankaner...
more...
As doubling from GIMB to VG is still pending, I doubt, we'll get the Electrification completed within your mentioned date.
Length Commissioned up to Mar 2019 = 96.95 Km out of 182.23 Km. Target 2019-20 : 59.58 Km Work is in progress. 42.85 Km track linked. Work also is in progress in balance section. Expected Completion for entire section: 2021-22 (Subject to construction of 2 NO. of ROB on NHAI on both the apprach. of Malya-Miyanya Station.)