Jun 20 2013 (15:01) 15813X/Arunachal MG Express | TZTB/Tezpur (1 PFs)
MailguardSG25~
MailguardSG25~ 24054 blog postsNormally 579 km(excluding Branch Lines & yards so totally 700-750 km) Gauge Conversion in IR(MG-BG) should take how many years?
I think it depends on fund allocation. If IR provide more manpower then project can be completed in short time frame...
Is this station converted to BG ? Or moved to another place with new name Dekargaon ?
Rangiya - Murkongselek including link fingers (511.88 Km ) (National Project)
Project Detail: click here
Project Detail: click here
Dekargaon station is 7 km far form Tezpore station . .
Dekargaon -Tezpore GC will be done later , as there is some problem.
Dekargaon -Tezpore GC will be done later , as there is some problem.
As of March 2013 Rangiya - Rangapara North Section of RNY - MZS Project (123.6 Km) is completed. Only Ballast supply work is in progress. Soon this section will operational.