Feb 01 (22:15) Chennai Metro Begins Tunnelling Work on Corridor-4 of Phase-2
Entry# 5958649   
  Past Edits
This is a new feature showing past edits to this News Post.
Chennai: CMRL starts tunnelling 2.1-km stretch from Panagal Park to Kodambakkam

Chennai Metro Rail Limited started tunnelling work for a 2.1-km underground stretch from Panagal Park in T Nagar to Kodambakkam, part of the corridor-4 under the second phase. The tunnelling machine, Pelican, will operate at a maximum depth of 18.5m and is expected to complete the work by December 2024. This...
more...
machine will pass under the North Usman Road and Kodambakkam flyovers. After completion, it will start tunnelling from Panagal Park towards Boat Club Station. Another tunnel boring machine, Peacock, will begin work on April 1st, 2024, from Panagal Park to Kodambakkam Powerhouse Ramp. The 26.1-km corridor-4 is part of the 116.1-km phase-2, which is scheduled for completion in stages between 2025 and 2028.

Chennai Metro Rail Limited ne Wednesday ko Panagal Park, T Nagar se Kodambakkam tak 2.1-km underground stretch ke liye tunnelling ka kaam start kiya hai. Ye corridor-4 ka hissa hai, jo second phase ka kaam hai. Pelican naam ka tunnel boring machine, 18.5m ki maximum depth pe kaam karega aur December...
more...
2024 tak khatam hone ki umeed hai. Ye machine North Usman Road aur Kodambakkam flyover ke neeche se gujarega. Kaam khatam hone ke baad, ye Panagal Park se Boat Club Station ki taraf tunnelling shuru karega. Ek aur tunnel boring machine, Peacock, April 1st, 2024 ko Panagal Park se Kodambakkam Powerhouse Ramp tak kaam shuru karega. 26.1-km corridor-4, 116.1-km phase-2 ka hissa hai, jiske stages mein 2025 aur 2028 ke beech complete hone ki ummeed hai.
Scroll to Top
Scroll to Bottom
Go to Desktop site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy