Updates regarding GIMB-SIOB and MALB-WKR Electrification- 1). Gandhidham Junction-Samkhiyali A). Hole digging has almost completed on Gandhidham. B). Hole digging and poles placed on Bhachau. C). No trace of work at Samakhiayali D).... more...
Foundation holes dug from Bhachau to Samakhiayali. 2. Maliya Miyana-Wakaner A). No trace of work at Maliya Miyana B). Poles placed on entire route. Only wiring remains pending!!! C). No trace of work at Wankaner. THANKS FOR READING!!!
Yo, here's the latest on GIMB-SIOB and MALB-WKR Electrification:
1) Gandhidham Junction-Samkhiyali:
A) They've almost finished digging holes in Gandhidham.
B) They dug the holes and put up the poles in Bhachau.
C) Ain't no sign of work happening in Samakhiyali.
D) They've dug foundation holes from Bhachau to Samakhiyali.
2) Maliya Miyana-Wakaner:
A) Nothing's happening in Maliya Miyana, man.
B) Poles are up along the whole route. Only gotta wire that sh*t up!
C) No work happening in Wankaner.
THANKS FOR READING!!!
Important Note:This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks. Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.