Track: Construction - Doubling+Electrification

Type of Station: Regular
Number of Platforms: 3
Number of Halting Trains: 23
Number of Originating Trains: 14
Number of Terminating Trains: 12
Falaknuma, Hyderabad
State: Telangana
Elevation: 522 m above sea level
Zone: SCR/South Central
Division: Hyderabad Deccan Nampally
1 Travel Tips
No Recent News for FM/Falaknuma
Nearby Stations in the News

Rating: 4.6/5 (14 votes)
cleanliness - excellent (2)
porters/escalators - excellent (2)
food - excellent (2)
transportation - excellent (2)
lodging - good (1)
railfanning - excellent (1)
sightseeing - excellent (2)
safety - average (2)

Nearby Stations

HPG/Huppuguda 1 km     YKA/Yakutpura 3 km     DQR/Dabirpura 4 km     MXT/Malakpet 5 km     NSVP/NPA Shivram Pally 5 km     BDVL/Budvel 7 km     KCG/Hyderabad Kacheguda 7 km     VAR/Vidya Nagar 9 km     JOO/Jamai Osmania 10 km     ATC/Arts College 11 km    

Station News

Page#    Showing 1 to 13 of 13 News Items  
Mar 23 2017 (08:43)  Hyderabad–Mahbubnagar track doubling works from Saturday (www.thehansindia.com)
back to top
Other NewsSCR/South Central  -  

News Entry# 297254   Blog Entry# 2207548     
   Tags   Past Edits
Mar 23 2017 (08:43)
Station Tag: Karimnagar/KRMR added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Morthad/MRTD added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Hyderabad Deccan Nampally/HYB added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Lingamguntla/LIN added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: KSR Bengaluru City Junction (Bangalore)/SBC added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Nizamabad Junction/NZB added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Medchal/MED added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Bolarum/BMO added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Malkajgiri Junction/MJF added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Secunderabad Junction/SC added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Hyderabad Kacheguda/KCG added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Falaknuma/FM added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Umdanagar/UR added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Mahbubnagar Town Halt/MHBT added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Station Tag: Mahbubnagar/MBNR added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Train Tag: Bodhan - Mahbubnagar Passenger/57474 added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Train Tag: Kacheguda - Mahbubnagar DEMU/77671 added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Train Tag: Mahbubnagar Mirzapalli Passenger/57448 added by Shiek Kaleem~/1676605

Mar 23 2017 (08:43)
Train Tag: Kacheguda Mahbubnagar Passenger/57447 added by Shiek Kaleem~/1676605

Posted by: eid ul fitr mubarak~  1 news posts
TRS MP and its Parliamentary Party Leader, A P Jithender Reddy, here on Wednesday, said that the work on the Hyderabad-Mahbubnagar Railway Line Doubling project and electrification at a cost of Rs 774 crore would begin on March 25.
Railway Minister Suresh Prabhu would lay the foundation stone for the project by remote control from Hyderabad.
Disclosing this to the media, Jithender Reddy said on Wednesday that the doubling work could be extended up to Benguluru later. Work on the present stretch would be completed in two-and-a-half years.
The
...
more...
line would be of great help to the people travelling from Mahbubnagar everyday to Hyderabad. Similarly, an e-Postal Passport office would be inaugurated in Mahbubnagar on March 31. 
He hailed the developmental works undertaken by the KCR led TRS government and said there was multipronged development in the State and it was racing towards the goals of 'Bangaru Telangana'.
In a separate statement, TRS MP K Kavitha's office informed media that the Morthad-Nizamabad Railway line would become operational on March 25.

3 posts - Thu Mar 23, 2017 - are hidden. Click to open.

4454 views
Mar 24 2017 (01:16)
eid ul fitr mubarak~   254 blog posts   1 correct pred (25% accurate)
Re# 2207548-4            Tags   Past Edits
Yes it is just laying foundation.
Jan 25 2017 (15:11)  Decks cleared for MMTS Phase II (www.thehansindia.com)
back to top
New Facilities/TechnologySCR/South Central  -  

News Entry# 292257     
   Tags   Past Edits
Jan 25 2017 (15:11)
Station Tag: Ram Chandra Pur/RCPH added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:11)
Station Tag: Bhel Halt/BHEL added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:11)
Station Tag: Lingampalli/LPI added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:11)
Station Tag: Umdanagar/UR added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:11)
Station Tag: Falaknuma/FM added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:11)
Station Tag: Secunderabad Junction/SC added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Posted by: ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~  95 news posts
Hyderabad: The Multi-Modal Transport System (MMTS) Phase II would get operational from December 2017 and the 75-km project would be commissioned in its entirety by 2018, said SCR new general manager Vinod Kumar Yadav.
Briefing the media at Charlapalli station here on Tuesday during a media tour between Secunderabad-Charlapalli-Ghatkesar, he said the completion of the MMTS Phase II is a top priority along with safety of rail passengers.
About 45-km length with 15-km track linking has been completed.The contentious 3.85 km defence land issue at Suchitra centre and 0.20 km
...
more...
defence land at Bhudevi Nagar-Ammuguda is sorted out and the Local Military Authority is waiting for an official letter from the Central government. With land acquisition in major corridors complete and the remaining land issues at the end stage, the MMTS Phase II work is going to speed up.
In December, Telapur-Ramchandrapuram corridor would start operations followed by Secunderabad-Moula Ali-Ghatkesar, said the general manager.
“The connectivity to Rajiv Gandhi International Airport (RGIA) is under discussion with the Ministry of Civil Aviation. We are hopeful that it would come through,” said the general manager. Out of the 10 acres land to be acquired, seven acres has already been acquired and the balance land is in advance stage of acquisition process, said Yadav.
The MMTS- Phase II services will cover Secunderabad-Moula Ali-Ghatkesar, Secunderabad-Bolarum-Medchal, Falaknuma-Umdanagar-Shamshabad Airport (Railways submitted sketch showing terminal station and consent from GMR is awaited), Moula Ali-Sanatnagar, Moula Ali-Malkajgiri-Sitafalmandi and Telapur-Ramchandrapuram stretches.
Five new stations
Five new stations are being constructed on Moula Ali-Sanatnagar route at Ferozguda, Suchitra Centre, Bhudevi Nagar, Neredmet and Moula Ali HB Colony. Three stations, namely Telapur, BHEL and Ramchandrapuram will be restored on Telapur-Ramchandrapuram section.
The MMTS-Phase II project was sanctioned in 2012-13 at an estimated cost of Rs 817 crore. The project is being done on cost sharing basis with the state government contributing 2/3rd of the cost. Till date, the Telangana government released just Rs 60 crore. Railway officials said that they are in talks with the state government for the release of Rs 160 crore in this financial year.
New terminal at Cherlapally
A new terminal at Cherlapally has been sanctioned and would be developed at a cost of Rs 80 crore. Six new platforms would be developed. The SCR general manager said the Railways has 50 acres of land and has put in a request for 150 acres from the state government. He met the Telangana State Chief secretary last week in this regard.
Jan 25 2017 (15:09)  MMTS to chug into Tellapur-R C Puram stretch by Dec (timesofindia.indiatimes.com)
back to top
New Facilities/TechnologySCR/South Central  -  

News Entry# 292256   Blog Entry# 2139806     
   Tags   Past Edits
Jan 25 2017 (15:12)
Station Tag: Bhel Halt/BHEL added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:12)
Station Tag: Hyderabad Kacheguda/KCG added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:12)
Station Tag: Moula Ali/MLY added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:12)
Station Tag: Umdanagar/UR added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:12)
Station Tag: Falaknuma/FM added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Jan 25 2017 (15:12)
Station Tag: Secunderabad Junction/SC added by ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~/1366147

Posted by: ⭐ ⭐ ⭐ Telangana Express Oops AP Express ⭐ ⭐ ⭐~  95 news posts
HYDERABAD: After a wait of four years, a part of Phase II of the Multi-Model Transport System (MMTS) is finally set to see light of the day by the end of this year. Vinod Kumar Yadav, general manager, South Central Railway, announced on Tuesday that the 5.75 km long Tellapur-R C Puram stretch will be the first in Phase II to get operational by December 2017. Subsequently, the entire project will be rolled out by December 2018.
On Tuesday, Yadav, who has recently taken charge, took mediapersons on a tour of the ongoing work being carried out on the Secunderabad-Moula Ali-Cherlapally-Ghatkesar section.
Totaling
...
more...
96.25 km, the Phase II project is spread across six routes. The total cost of the project is Rs 817 crore. This will be shared between the state government (it is supposed to pay two-thirds of the cost) and the SCR authorities.
Being implemented by the Rail Vikas Nigam Limited (RVNL), this phase of the venture is still ridden with a few roadblocks. Among them is the issue of building a station at the Shamshabad airport -- a proposition being opposed tooth and nail by the airport authorities. There is also the issue of acquiring defence land along the Sanathnagar-Moula Ali stretch. In both cases, central ministries (civil aviation and defence) have now intervened to resolve the crisis.
"We have already taken up the issue with the concerned ministry and are hopeful of sorting out hurdles at the earliest," the newly sworn-in general manager said. He also confirmed that the MMTS connectivity to Yadadri - which too was on hold for a while --- has been sanctioned and the final location survey now is complete. "Tenders will be invited by April 20," he said.
On the issue of developing the Cherlapally station as a 'satellite terminal' - which will help decongest the traffic, of both long-distance and MMTS trains - he said that SCR has sought 150 acres of land from the state government for the same. The new terminal will be armed with six platforms and additional passenger/maintenance facilities. The project is expected to cost Rs 80 crore.
"The satellite terminal is meant to lessen the burden on Secunderabad railway station. Works in this regard have already been commenced. SCR has identified 50 acres of land and is in discussion with the state to acquire another 150 acres," he added.
Further, on the sidelines of the tour, Yadav pointed out that "safety" of passengers would be a prime area of focus for his team, during his tenure. He also stressed on improved mobility and punctuality. "SCR is according top priority to safety. Drives have been initiated to check railway tracks and rolling stock, including coaches and wagons," he said. He also mentioned that a new system for employee redressal has been put in place where a staff member can directly approach the general manager, if the grievance remains unresolved for a month.

3596 views
Jan 25 2017 (16:11)
Venkat వెంకట్   3243 blog posts   1 correct pred (100% accurate)
Re# 2139806-1            Tags   Past Edits
Thats a welcome move. They can make a bigger bus terminal at Patancheru near by this station and can terminate some of the buses from Karnataka, Maharasatra side. It helps to control traffic also.

3469 views
Jan 25 2017 (17:02)
Srikanth~   1601 blog posts   588 correct pred (72% accurate)
Re# 2139806-2            Tags   Past Edits
I guess, Secunderabad (SC) will be even more congested with SC - MLY - Cherlapally- Ghatkesar line. Important, passing through & RSA trains might not terminate at Charlapally. Only weekly trains might terminate. Tellapur - RC Puram is welcome.

3410 views
Jan 25 2017 (17:10)
Venkat వెంకట్   3243 blog posts   1 correct pred (100% accurate)
Re# 2139806-3            Tags   Past Edits
If they can create terminal at RC puram, then some train can be extended to RC to decongest the SC.
3rd line is almost impossible in Begumpet - SC sector
Sep 03 2016 (20:59)  Special Trains Run to clear rush of Passengers in Twin Cities (www.scr.indianrailways.gov.in)
back to top
New/Special TrainsSECR/South East Central  -  IR Press Release  

News Entry# 279033     
   Tags   Past Edits
Sep 03 2016 (8:59PM)
Station Tag: Lingampalli/LPI added by kab mere acche din aayenge~/573824

Sep 03 2016 (8:59PM)
Station Tag: Hyderabad Deccan Nampally/HYB added by kab mere acche din aayenge~/573824

Sep 03 2016 (8:59PM)
Station Tag: Falaknuma/FM added by kab mere acche din aayenge~/573824

Sep 03 2016 (8:59PM)
Station Tag: Secunderabad Junction/SC added by kab mere acche din aayenge~/573824

Posted by: Sunny Babu Brother of sampoornesh babu~  51 news posts
In order to clear the extra rush of passengers due to Buses and Auto strike today, South Central Railway has run 14 special trains today i.e., 2ndSeptember, 2016 between various destinations in the twin cities of Hyderabad and Secunderabad. These special trains are in addition to the regular 121 MMTS Train services which ran normally.

The special trains run today are as follows:-
...
more...

1.Secunderabad-Falaknuma – 01 DEMU special
2.Falaknuma-Lingampalli – 02 DEMU specials
3.Secunderabad-Lingampalli – 03 MEMU specials
4.Lingamaplli-Hyderabad – 02 MEMU specials
5.Hyderabad-Lingampalli – 02 MEMU specials
6.Lingampalli-Falaknuma ­ – 03 DEMU specials
7.Kacheguda-Lingampalli ­– 01 DEMU special
Jul 29 2016 (15:21)  FALAKNUMA - GULBARGA/57660 timings revised (www.scr.indianrailways.gov.in)
back to top
IR Press Release  

News Entry# 275292     
   Tags   Past Edits
Jul 29 2016 (3:21PM)
Station Tag: Gulbarga/GR added by ✿ఛుక్ 🚃 ఛుక్ 🚃 రైలు✿~/576746

Jul 29 2016 (3:21PM)
Station Tag: Secunderabad Junction/SC added by ✿ఛుక్ 🚃 ఛుక్ 🚃 రైలు✿~/576746

Jul 29 2016 (3:21PM)
Station Tag: Falaknuma/FM added by ✿ఛుక్ 🚃 ఛుక్ 🚃 రైలు✿~/576746

Jul 29 2016 (3:21PM)
Train Tag: Falaknuma - Gulbarga Passenger/57660 added by ✿ఛుక్ 🚃 ఛుక్ 🚃 రైలు✿~/576746

Posted by: ✿ఛుక్ 🚃 ఛుక్ 🚃 రైలు✿~  54 news posts
Timings revised for 57660 fm-Gr
Departures
Fm 05:00hrs
Sc 05:45/05:55hrs
Page#    Showing 1 to 13 of 13 News Items  

Scroll to Top
Scroll to Bottom


Go to Desktop site
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.