The train from Kannur today arrived at Banaswadi at 6:20am which was a delay of 15 min. As per the NTES it departed from the station only at 7:30am which meant it stopped for more than 1 hour. Finally it reached Yeswantpur at 8:10 with a delay of just 10min.
It is high time the slack between these station is reduced. Just to cover a distance of 15km almost 2 hours is provided as slack time !!!......pity those passengers who have to travel till YPR. They could as well get down at Banaswadi take another mode of transport and still reach Yesvantpur before the train !!
It is high time the slack between these station is reduced. Just to cover a distance of 15km almost 2 hours is provided as slack time !!!......pity those passengers who have to travel till YPR. They could as well get down at Banaswadi take another mode of transport and still reach Yesvantpur before the train !!
1 Posts
The complaint was posted (by the regular passengers) and got the standard reply.
1. Noted. Will be examined
2. The representation is noted with concern. All concerned will be advised to look into the matter and do the needful.
3. Diversion of trains pertains to Railway Board being a policy matter. Hence reverting back is not feasible.
4....
more...
1. Noted. Will be examined
2. The representation is noted with concern. All concerned will be advised to look into the matter and do the needful.
3. Diversion of trains pertains to Railway Board being a policy matter. Hence reverting back is not feasible.
4....
more...
I guess it is another easy way to show more punctuality for trains. I feel sorry for those passengers who get down at YPR....At least they can reach an hour early if so much slack was not given.
This train needs huge slack,reason is single ghat section from Subramanya to Sakleshpura
If there are no crossings at ghat sections it reaches Before time at all stations in Up and down direction.
If there is atleast one crossing means it wil get more delayed
If there are no crossings at ghat sections it reaches Before time at all stations in Up and down direction.
If there is atleast one crossing means it wil get more delayed
It is not 16517 via Mangalore. It is via PGT/SA.
16518 is sleeping two hours at MAQ.
16518 is sleeping two hours at MAQ.
Reached early and got RED at BAND outer-Army area. Better to get down and proceed further. Right side few meters will get Chikka Banasawadi Road. Further around less than a KM will get the Banasawadi Main Road (Ayyappa Temple).