Apr 07 2017 (20:29) 12362/Mumbai CSMT - Asansol SF Express (PT) | MKP/Manikpur Junction (4 PFs) | SGUJ/WDG-4/12155
IndianRailwayslover~
IndianRailwayslover~ 2234 blog postsHere's some update about electrification between Cheoki and Manikpur.. The stretch between Manikpur and Shankargarh is not completely electrified. There is no OHE in Manikpur yet and there are few places between Manikpur and Shankargarh without OHE but the work is going on at a good pace.. Shankargarh to Cheoki is completely electrified infact there is rail line being created near Shankargarh to plant located at that area..
#etaldelectrificationupdate
#etaldelectrificationupdate
5 Posts
#etaldelectrificationupdate
Katni to Jabalpur
There is not enough changes to what I saw last time. Electric poles are erected on few stretches but the electrification is moving at a very slow pace.. Although poles can be found laying down between Katni and Dundi..
Jabalpur to Pipariya
No...
more...
Katni to Jabalpur
There is not enough changes to what I saw last time. Electric poles are erected on few stretches but the electrification is moving at a very slow pace.. Although poles can be found laying down between Katni and Dundi..
Jabalpur to Pipariya
No...
more...
Absolutly bro...the work of erecting holes on MML station was started with the great speed but now the work is again gone slow, they had erected the holes on half of the platform and then the work is stopped now. I think the work of ET-ALD will not be completed by the deadlines given by the CORE. It will takes approx. two years to complete the whole section.😶😖
Yes pace is very slow brother.. I agree it may take upto 2 more years
I don't know why the work is getting slower and slower, as in this year budget they got sufficient amount then also its getting slow...🙁