BHUBANESWAR: Nayagarh was put on the railway map of the country Monday when railway minister Suresh Prabhu formally dedicated the new line from Bolagarh Road to...
After struggling for several years, the E-W connectivity project KhurdaRd-Bolangir new line project has finally gathered momentum and we can expect completion in next 4-5 years.
* 1945-Survey conducted for KhurdaRd-Bolangir new rail line
* 1994-95- Project sanctioned- but didnot pickup due to lack of funds
* 2016-36kms long KhurdaRoad-Begunia- First phase commissioned (it took more than 2 decades for first section to...
more...
* 1945-Survey conducted for KhurdaRd-Bolangir new rail line
* 1994-95- Project sanctioned- but didnot pickup due to lack of funds
* 2016-36kms long KhurdaRoad-Begunia- First phase commissioned (it took more than 2 decades for first section to...
more...