Itarsi-Manikpur-Allahabad Electrification Project Update - 2018
TRIAL of electricity-operated Rail Engines was carried out successfully on 178 km route of Piparia-Jabalpur on Sunday
This was carried out under West Central Railway's Mission Electrification in Madhya Pradesh
The Itarsi- Jabalpur block of 245km will also be switched from Diesel-operated to Electricity operated, in the month of January, after undergoing an inspection by Commissioner Railway Security
The Indian Railways have undertaken this mission for the hundred percent electrification of Rail routes by year 2021
This will lead to an estimated annual saving of fuel worth 150 crore Rupees, along-with saving the time consumed in the shifting of Locomotives and increasing the speed of the trains
The WCR has taken up a target of electrification of 1313 kilometers
The Officers of Central Rail Electrification Organization (Core) and workers of WCR contributed immensely to the success of the trial
It is to be noted that electrification of Pipariya-Jabalpur route is a part of the Itarsi-Manikpur-Allahabad Electrification Project
Jan 01 2018 (09:45)
Station Tag: Madan Mahal/MML added by indianrailwayuser~/1693450
Jan 01 2018 (09:45)
Station Tag: Pipariya/PPI added by indianrailwayuser~/1693450
Jan 01 2018 (09:45)
Station Tag: Jabalpur Junction/JBP added by indianrailwayuser~/1693450
Jan 01 2018 (09:45)
Station Tag: Itarsi Junction/ET added by indianrailwayuser~/1693450
Jan 01 2018 (09:41)
Jan 01 2018 (09:34)
Loco Tag: JHS/WDG-3A/16212 removed by indianrailwayuser~/1693450
Jan 01 2018 (09:34)
Loco Tag: JHS/WDG-3A/16212 removed by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: JHS/WDG-3A/18880R added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: JHS/WDG-3A/16212R added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: JHS/WDG-3A/16212 added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: CLA/WDG-3A/14812 added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: CLA/WDG-3A/14850 added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
ET PPI JBP ELECTRIFICATION UPDATE - 2018
KURLA BROTHERS & BANARASI BABU TALKING ON THIS NEW DEVELOPMENT IN KEQ FEW DAYS BACK
Itarsi-Manikpur-Allahabad Electrification Project Update - 2018
TRIAL of electricity-operated Rail Engines was carried out successfully on 178 km route of Piparia-Jabalpur on Sunday
This was carried out under West Central Railway's Mission Electrification in Madhya Pradesh
The Itarsi- Jabalpur block of 245km will also be switched from Diesel-operated to Electricity operated, in the month of January, after undergoing an inspection by Commissioner Railway Security
The Indian Railways have undertaken this mission for the hundred percent electrification of Rail routes by year 2021
This will lead to an estimated annual saving of fuel worth 150 crore Rupees, along-with saving the time consumed in the shifting of Locomotives and increasing the speed of the trains
The WCR has taken up a target of electrification of 1313 kilometers
The Officers of Central Rail Electrification Organization (Core) and workers of WCR contributed immensely to the success of the trial
It is to be noted that electrification of Pipariya-Jabalpur route is a part of the Itarsi-Manikpur-Allahabad Electrification Project
Jan 01 2018 (09:45)
Station Tag: Madan Mahal/MML added by indianrailwayuser~/1693450
Jan 01 2018 (09:45)
Station Tag: Pipariya/PPI added by indianrailwayuser~/1693450
Jan 01 2018 (09:45)
Station Tag: Jabalpur Junction/JBP added by indianrailwayuser~/1693450
Jan 01 2018 (09:45)
Station Tag: Itarsi Junction/ET added by indianrailwayuser~/1693450
Jan 01 2018 (09:41)
Jan 01 2018 (09:34)
Loco Tag: JHS/WDG-3A/16212 removed by indianrailwayuser~/1693450
Jan 01 2018 (09:34)
Loco Tag: JHS/WDG-3A/16212 removed by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: JHS/WDG-3A/18880R added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: JHS/WDG-3A/16212R added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: JHS/WDG-3A/16212 added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: CLA/WDG-3A/14812 added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
Loco Tag: CLA/WDG-3A/14850 added by indianrailwayuser~/1693450
Jan 01 2018 (09:33)
ET PPI JBP ELECTRIFICATION UPDATE - 2018
KURLA BROTHERS & BANARASI BABU TALKING ON THIS NEW DEVELOPMENT IN KEQ FEW DAYS BACK
ET PPI JBP ELECTRIFICATION UPDATE - 2018
ET JBP Electrification trial OK. CRS NEXT
KURLA BROTHERS & BANARASI BABU TALKING ON THIS NEW DEVELOPMENT IN KEQ FEW DAYS BACK.
Itarsi-Manikpur-Allahabad Electrification Project Update - 2018
TRIAL...
more...
ET JBP Electrification trial OK. CRS NEXT
KURLA BROTHERS & BANARASI BABU TALKING ON THIS NEW DEVELOPMENT IN KEQ FEW DAYS BACK.
Itarsi-Manikpur-Allahabad Electrification Project Update - 2018
TRIAL...
more...
of electricity-operated Rail Engines was carried out successfully on 178 km route of Piparia-Jabalpur on Sunday. This was carried out under West Central Railway's Mission Electrification in Madhya Pradesh.
The Itarsi- Jabalpur block of 245km will also be switched from Diesel-operated to Electricity operated, in the month of January, after undergoing an inspection by Commissioner Railway Security.
The Indian Railways have undertaken this mission for the hundred percent electrification of Rail routes by year 2021. This will lead to an estimated annual saving of fuel worth 150 crore Rupees, along-with saving the time consumed in the shifting of Locomotives and increasing the speed of the trains.
The WCR has taken up a target of electrification of 1313 kilometers.
The Officers of Central Rail Electrification Organization (Core) and workers of WCR contributed immensely to the success of the trial. It is to be noted that electrification of Pipariya-Jabalpur route is a part of the Itarsi-Manikpur-Allahabad Electrification Project.
The Itarsi- Jabalpur block of 245km will also be switched from Diesel-operated to Electricity operated, in the month of January, after undergoing an inspection by Commissioner Railway Security.
The Indian Railways have undertaken this mission for the hundred percent electrification of Rail routes by year 2021. This will lead to an estimated annual saving of fuel worth 150 crore Rupees, along-with saving the time consumed in the shifting of Locomotives and increasing the speed of the trains.
The WCR has taken up a target of electrification of 1313 kilometers.
The Officers of Central Rail Electrification Organization (Core) and workers of WCR contributed immensely to the success of the trial. It is to be noted that electrification of Pipariya-Jabalpur route is a part of the Itarsi-Manikpur-Allahabad Electrification Project.