5 crossings for RC yesterday, in 25 km KNP-LD section !!
1.17317 UBL-LTT was looped at KNP, waiting for RC, as this was 1 hr late.
2.Poorna Exp and Goa Exp were both looped at Gunji, waiting for RC to arrive at Gunji. Goa left before Poorna.
RC was made to wait at Gunji, as 11022 Dadar Exp was running 2...
more...
1.17317 UBL-LTT was looped at KNP, waiting for RC, as this was 1 hr late.
2.Poorna Exp and Goa Exp were both looped at Gunji, waiting for RC to arrive at Gunji. Goa left before Poorna.
RC was made to wait at Gunji, as 11022 Dadar Exp was running 2...
more...
LTT-UBL Exp too stuggles between BGM-Londa-Alnavar, first gets held up at BGM by Castle Rock-MRJ pass, then crossings with RC, Ajmer/Jodhpur trains between BGM-Londa, between Londa-Alnavar due to Haripriya.
Any progress of doubling in Londa-BGM section, is track laid anywhere in that section ??
Any progress of doubling in Londa-BGM section, is track laid anywhere in that section ??
No.. only land levelling has been completed, that too in parts..