1. Base work not strted yet at NJP Jn+yard
2. Upline pole erection done till Mahanadi bridge near NJP
3. Downline pole not erected about 55-60km from NJP
4. Wiring not done btwn NJP- Aluabari road
2. Upline pole erection done till Mahanadi bridge near NJP
3. Downline pole not erected about 55-60km from NJP
4. Wiring not done btwn NJP- Aluabari road
wahi to, aur bolta he 2021 me whole network electrified korega