May 22 2019 (15:57) 11014/Coimbatore - Mumbai LTT Express (PT) | SUR/Solapur (5 PFs) | KJM/WDP-4D/40450
psanga_sur^~
psanga_sur^~ 5601 blog posts#PuneSolapurGulbargaDoubling
Bhigwan to Jeur - leveling work is in progress. RVNL will take another 5 years for this stretch.
Jeur to Bhalwani - 70% tracks laid and construction of platform at Jeur is in progress.
Bhalawani to Wadshinge - All the tracks are laid, signals are installed, construction of new platforms at Bhalawani, Kem, Dhavlas & Wadshinge are completed. Only interlocking...
more...
Bhigwan to Jeur - leveling work is in progress. RVNL will take another 5 years for this stretch.
Jeur to Bhalwani - 70% tracks laid and construction of platform at Jeur is in progress.
Bhalawani to Wadshinge - All the tracks are laid, signals are installed, construction of new platforms at Bhalawani, Kem, Dhavlas & Wadshinge are completed. Only interlocking...
more...
10 Posts
Why CRS inspection not taken complete work of wadhshinge Bhalwani route