Aug 13 2019 (21:16) 12158/Hutatma Express | KWV/Kurduwadi Junction (4 PFs)
psanga_sur^~
psanga_sur^~ 5601 blog posts#PuneSolapurGulbargaDoubling
To commission 35 Kms Wadshinge - Bhalawani section and interlocking work 1 week black is sanctioned by RB.
None of the train in this period will run due to changing of alignment of existing track and Kurduwadi yard remodeling work.
Few key points.
1....
more...
To commission 35 Kms Wadshinge - Bhalawani section and interlocking work 1 week black is sanctioned by RB.
None of the train in this period will run due to changing of alignment of existing track and Kurduwadi yard remodeling work.
Few key points.
1....
more...
34 Posts
How it is possible? Gulbarga sawalgi is nearing completion after that works are going on till boroti. Then after wadshinge till Bhigvan is remaining. I'm travelling on sept 1 will check and give updated information.
Kulkarni Sir is asking about progress of Solapur - Daund section only.
Without track linking how crs wd be completed please let us know.