Doubling and electrification updates few kms outside Dharwad towards Hubli.
When can we expect commissioning ofdoubling between Hubballi and Dharwad?
From UNKAL to Navalur tracks along with ohe has been laid and from Navalur to DWR only ohe poles have been laid still tracks are not laid. From UBL to Unkal levelling is going on and is almost completed. It will take another maximum 8-10 months for doubling to complete.
Minimum six months, sleepers and ballasts are being laid between ubl and dwr. But there are few ROBs (Hubli, Navalur, Dharwad) which have to broadened to accomodate the second line. The work has begun in hubli and Dharwad but Navalur is pending.