Updates regarding GIMB-SIOB and MALB-WKR Electrification-
1). Gandhidham Junction-Samkhiyali
A). Hole digging has almost completed on Gandhidham.
B). Hole digging and poles placed on Bhachau.
C). No trace of work at Samakhiayali
D)....
more...
1). Gandhidham Junction-Samkhiyali
A). Hole digging has almost completed on Gandhidham.
B). Hole digging and poles placed on Bhachau.
C). No trace of work at Samakhiayali
D)....
more...
9 Posts
I did not travel towards Bhuj for last few months, so no idea for work in and around Bhuj.
Foundation holes have been made all way till BHUJ. And only wiring remains between GIMB SIOB.
Yes, poles have been ercted all the way from SIOB to GIMB. Wiring is pending.
When completed Bhuj GANDHIDHAM or Gandhidham viramgam section electrification any updates
SIOB to VG no work of Electrification as doubling is pending in various patches.
GIMB to Adipur Poles have been erected. Beyond that no idea as of now as I haven't travel either by road or rail towards BHUJ.
GIMB to Adipur Poles have been erected. Beyond that no idea as of now as I haven't travel either by road or rail towards BHUJ.