11 kms of GC work left between LTA & SMC. Interesting thing that DB mentioned is that RB has ordered not to begin operation before electrification. Dense forest have made it tough to carry out electrification work.
#JBPBTCGC
#JBPGELECTRIFICATION
#JBPBTCGC
#JBPGELECTRIFICATION
9 Posts
Baki k 11 km. k section me bhi agar earth work and bridges ka kam ho gaya h to mansoon me bhi track bichhane ka kam ho sakta h,
Aise me jyada dikkat nhi aayegi..
Aise me jyada dikkat nhi aayegi..
Earthwork complete ho chuka hai or ab Titwa se Magardarra ke bich 6-7 km me track Linking (specially forest area me) bach gai hai jiske liye sleepers or track side me rakhe jaa chuke hai.
To fir to mansoon me bhi koi dikkat nhi aayegi, time se work complete ho jayega..