Jan 30 2022 (16:10) INDB/Indore Junction (6 PFs)
TouristerDivyanshu^~
TouristerDivyanshu^~ 172564 blog posts17 Posts
Indore metro project update
✅55% work completed
✅13 months left for trial
✅Now preparing for fourth launcher
✅MPMRC...
more...
✅55% work completed
✅13 months left for trial
✅Now preparing for fourth launcher
✅MPMRC...
more...
Indore Metro Update🚇
⏩Trial run from Gandhinagar to ISBT in 5.9km stretch instead of 17.5km by 2023.
⏩Claims to complete leftover 11.6km stretch by 2024.
...
more...
⏩Trial run from Gandhinagar to ISBT in 5.9km stretch instead of 17.5km by 2023.
⏩Claims to complete leftover 11.6km stretch by 2024.
...
more...
Indore Metro Update🚇
✅According to officials, about 70% of the Metro work on the Super Corridor has been completed.
✅The second launcher will be launched here till October 15.
...
more...
✅According to officials, about 70% of the Metro work on the Super Corridor has been completed.
✅The second launcher will be launched here till October 15.
...
more...