Jun 09 2023 (20:52) 12957/Swarna Jayanti Rajdhani Express | PNU/Palanpur Junction (5 PFs)
riz339~
riz339~ 5606 blog posts(i) Mahesana- Bhandu Motidau (7.89 Km) - Earthwork (90%), Minor bridges (90%), Major bridges (90%) completed. 3 Km track Linking completed. Platform work at Bhandu Moti Dau is in progress(30%).
(ii) Palanpur – Dharewada (24.19Km)-Dec-23: Earthwork (0.53/1.5)(35%), Important Bridge (1/1)(70%) & major bridges (1/1)(5%) completed.
(iii)...
more...
(ii) Palanpur – Dharewada (24.19Km)-Dec-23: Earthwork (0.53/1.5)(35%), Important Bridge (1/1)(70%) & major bridges (1/1)(5%) completed.
(iii)...
more...
2 Public Posts - Sat Jun 10, 2023
Thanks for update as any idea by when whole palanpur mehsana doubling will be completed?
3 Public Posts - Sat Jun 10, 2023
1 Public Posts - Fri Jun 23, 2023