At last SECR has said that work between NIR-Samnapur will complete within 31 June 2019 so hopefully in July CRS will b invited for inspection of NIR-Samnapur section and may b by Aug 2019 we can see new trains on this section so hope for the best
#NIRSAMNAPURBGUPDATES
#JBPGBGPROJECTUPDATES
At last SECR has said that work between NIR-Samnapur will complete within 31 June 2019 so hopefully in July CRS will b invited for inspection of NIR-Samnapur section and may b by Aug 2019 we can see new trains on this section so hope for the best
4 Public Posts - Mon Apr 22, 2019
2 Public Posts - Fri May 17, 2019
4 Public Posts - Sat May 18, 2019
1 Public Posts - Sun Jun 23, 2019
2 Public Posts - Sat Jul 06, 2019
1 Public Posts - Thu Jul 11, 2019
1 Public Posts - Sun Sep 29, 2019
#jbpnews
#JBPGBGPROJECTUPDATES
MP Rakesh Singh told the reporters after the meeting with SECR GM and officls that NIR-Samnapur BG work will be completed by June 2019 and this will also complete the most important JBP-G BG project and NIR-Samnapur efication will also be completd by Sep 2019 and in this way JBP-NIR-G section will be fully electrified by Sep 2019 so lets hope this June 2019 deadline would be met by contractor
#JBPGBGPROJECTUPDATES
MP Rakesh Singh told the reporters after the meeting with SECR GM and officls that NIR-Samnapur BG work will be completed by June 2019 and this will also complete the most important JBP-G BG project and NIR-Samnapur efication will also be completd by Sep 2019 and in this way JBP-NIR-G section will be fully electrified by Sep 2019 so lets hope this June 2019 deadline would be met by contractor
6 Public Posts - Fri Jan 25, 2019
#NIRSAMNAPURBGUPDATES
#JBPGBGPROJECTUPDATES
#SECRNEWS
Now again a problem arised in completing BG work of Samnapur-NIR section that sleepers and rails for laying in this section is not being transported yet and there is shortage of both and RB also told zones to fasten pending works of projects which can be completed till March 2019 only and zone should give less preference to...
more...
#JBPGBGPROJECTUPDATES
#SECRNEWS
Now again a problem arised in completing BG work of Samnapur-NIR section that sleepers and rails for laying in this section is not being transported yet and there is shortage of both and RB also told zones to fasten pending works of projects which can be completed till March 2019 only and zone should give less preference to...
more...
4 Public Posts - Mon Jan 07, 2019
5 Public Posts - Wed Jan 09, 2019
Aug 02 2018 (17:59) 02827o/Jabalpur - Santragachi Humsafar Inaugural Special | JBP/Jabalpur (7 PFs)
robin~
robin~ 6144 blog posts#jbpnews
#JBPSRCHSINNAUGRALRUN
#JBPGBGPROJECTUPDATES
At last after so much drama the dream train of JBP run officially yesterday and inaugurated by MP Mr. Rakesh Singh and WCR GM Mr. Soyin and other WCR officials and its a biggest day for JBP people and JBP Railfans and no one expected the inaugural date this much fast due to lots of drama from RB...
more...
#JBPSRCHSINNAUGRALRUN
#JBPGBGPROJECTUPDATES
At last after so much drama the dream train of JBP run officially yesterday and inaugurated by MP Mr. Rakesh Singh and WCR GM Mr. Soyin and other WCR officials and its a biggest day for JBP people and JBP Railfans and no one expected the inaugural date this much fast due to lots of drama from RB...
more...
1 Public Posts - Thu Aug 02, 2018
#JBPGBGPROJECTUPDATES
#NIRSAMNAPURBGUPDATES
As per patrika news survey the officials of JBP-G BG projects indicates that work of BG b/w NIR-Samnapur will complete by JAN 2019 approx. if any big hurdle will not come and as per current progress of work so hopefully by Feb/March 2019 we can expect BG trains on NIR-Samnapur section of JBP-BTC route and currently earthwork is going on and work is resumed again
#NIRSAMNAPURBGUPDATES
As per patrika news survey the officials of JBP-G BG projects indicates that work of BG b/w NIR-Samnapur will complete by JAN 2019 approx. if any big hurdle will not come and as per current progress of work so hopefully by Feb/March 2019 we can expect BG trains on NIR-Samnapur section of JBP-BTC route and currently earthwork is going on and work is resumed again