Search Forum
PNR Entry# 1925167
Posted: Jul 10 2016 (17:52)
7 Responses
Last Response: Jul 13 2016 (18:01)
7 Responses
Last Response: Jul 13 2016 (18:01)
Journey: Mon Jul 11, 2016
Dep: WADI/Wadi Junction @ 16:40 PF#: 4
Arr: LTT/Mumbai LTT @ 04:15 +1 night
Distance: 585 km / 1495 km
Class: AC 2-tier - 2A | Tot Seats: Avbl-0004# | Charting @08:45
18519/Visakhapatnam - Mumbai LTT Express (Via Vijayawada) (PT)Dep: WADI/Wadi Junction @ 16:40 PF#: 4
Arr: LTT/Mumbai LTT @ 04:15 +1 night
Distance: 585 km / 1495 km
Class: AC 2-tier - 2A | Tot Seats: Avbl-0004# | Charting @08:45
PNR: 615-xxxxxxx | Similar PNRs
Entry# 1925167
NO PENDING REQUEST
Posted: Jul 10 2016 (17:52:21) View Posted Status
Latest Status: Jul 10 2016 (21:18:03)
Passenger 1: A1,27 [LB]/Coach Position:5 (Booking Status: W/L 7,RLGN)Total Fare: 1275
Chart NOT Prepared
2 Posts
Trip was great and reached Mumbai on time.
Some of the pics taken and update on Wadi-Gulbarga #electrification. Hirnenduru Station electrified.
a)Wadi station to Shahabad Station- Except for 17 poles, Rest all wiring done. Shahabad station wiring has started.
b) Shahabad Station Outer till Martur Station, Wiring almost done. Martur station wiring about to be started.
c)...
more...
Some of the pics taken and update on Wadi-Gulbarga #electrification. Hirnenduru Station electrified.
a)Wadi station to Shahabad Station- Except for 17 poles, Rest all wiring done. Shahabad station wiring has started.
b) Shahabad Station Outer till Martur Station, Wiring almost done. Martur station wiring about to be started.
c)...
more...
Updated on Gulbarga-Tilati #doubling
Pic1, Pic2 and Pic3: is UBL Twins hauling concor rake at Boroti. VSKP-LTT was overtaken by SC-Pune at boroti.
Pic4: Doubling work in progress from Boroti to Akalkot road, except minor bridges (civil work rest all done) and only track is to be laid.
Pic5: Doubling track work completed fully between Akalkot to Tilati. We can expect commissioning in...
more...
Pic1, Pic2 and Pic3: is UBL Twins hauling concor rake at Boroti. VSKP-LTT was overtaken by SC-Pune at boroti.
Pic4: Doubling work in progress from Boroti to Akalkot road, except minor bridges (civil work rest all done) and only track is to be laid.
Pic5: Doubling track work completed fully between Akalkot to Tilati. We can expect commissioning in...
more...
Thank you for the updates sir and interesting to know you literally counted the number of unwired poles :-)
Hahaha, yes boss,I am inquisitive enough and looking for speedy completion of electrification. even after Shahabad, I counted some 33 poles were unwired :)
We rail fans do all these things in life... Its amazing to hear :-) Also good to know that doubling work also started from Akkalkot road towards Nagansur/boroti.... Abb doubling dooor nahi hai :-)