What's the current status of doubling of bhigwan to gulbarga stretch and the electrification of Pune daund and manmad stretch?please can somebody post the pics
The latest status is as under:
.
PUNE-DD Electrification:
- No poles from Ghorpuri (Yard) outer to Hadapsar, reason might be pending shifting of some HT wires crossing tracks at low levels.
-...
more...
.
PUNE-DD Electrification:
- No poles from Ghorpuri (Yard) outer to Hadapsar, reason might be pending shifting of some HT wires crossing tracks at low levels.
-...
more...