Oct 06 2015 (16:03) DMWP/DMW Halt Patiala (1 PFs)
thetrainexplorer~
thetrainexplorer~ 3159 blog posts1 Posts
For almost an year they were kept under the sun, and they laid them in May 2015, and now extending them on both sides cuz of proposed doubling.
In my town, these girders were finished by almost April-May'15 & have been not installed yet. And so, the electrification project & RUB, both are delayed. But a lot of construction & demolition work is going on there & some sand-loaded trucks arrived yesterday.
See, it all depends on the traffic block. Ours got delayed for 4 months as UMB division was not allowing traffic block. The block was given in May2015 for just 4 hrs. And in these 4 hrs engineers had to cut the track section and lay the boxes.