Jul 03 2016 (15:43) 73432/Jamalpur - Sahibganj DEMU | BGP/Bhagalpur Junction (6 PFs)
Railadventures~
Railadventures~ 2770 blog postsPirpaiti to kahalgaon 22km doubling of track work is almost over may be next March after CRS passenger service may start. Some pics of Bikramshila station and doubling of this section pics click from inside the train .Only for these pics I visited these area personally with my friend.
#ErJA
#ErJA
7 Posts
But aap dekho Deoghar and hansdia rail line kab se tayyar thi crs kitna late hua
Usi hisab se Maine maxm March 2017 kha for clg to ppt doubling
Mai Apr mein aaya tha, I saw that pirpainti to svrp, 09 kms 80% tracks laid down for doubling, svrp to vikramshila east, soil work just started, vikramshila east to kahalgaon 60% tracks laid down.
Therefore, CRS may happen in feb after finishing remaining work in 05 months sep to jan as slow work will be done in jul Aug due to monsoon.
Similarly, I saw work just started between bgp and sabaur, but good amount of work in ghogha - lailakh section. After demolition of gopalpur bridge near sabaur, we may expect...
more...
Therefore, CRS may happen in feb after finishing remaining work in 05 months sep to jan as slow work will be done in jul Aug due to monsoon.
Similarly, I saw work just started between bgp and sabaur, but good amount of work in ghogha - lailakh section. After demolition of gopalpur bridge near sabaur, we may expect...
more...
Is area ko gorakhpur ke jorna chaiye ek weekly train to Howrah via bgp chala kar