Pune: The Central Railway (CR) plans to build a chord line on the Pune-Manmad route which will bypass Daund station and help speed up long distance...
read more... CR mulls chord line to bypass Daund station
9 Public Posts - Mon Oct 17, 2016
4 Public Posts - Tue Oct 18, 2016
120km of new line requires 1000-1200 cr and to complete in next 3 yrs requires 200 cr allocation in 2017-18 budget and should increase over the years. They are many lines all over the country which are surveyed premilinary works started Yeats back and still waiting for allocation and this line is surveyed in 2015-16 land acquisition has to be done and we can't expect it do be complete in next 3 yrs. The only alternative to cut some running time is to construct bypass at daund in 1yr on pirioity basis.
3 Public Posts - Tue Oct 18, 2016
1 Public Posts - Fri Oct 21, 2016