Can anyone please tell the progress of ongoing projects in South India (SWR,SCR,KR and SR)
18 Public Posts - Sun Mar 05, 2017
2 Public Posts - Mon Mar 06, 2017
Doubling projects and electrification at SWR:
1. Ramnagaram-Mysuru doubling and electrification: Doubling of 1.5km stretch at Srirangapatna pending due to shifting of Tipu's armory, it was completed few days ago, so expect doubling of whole stretch to be completed in 1-2 months, electrification in 3 months
2. Yelahanka-Penukonda doubling and electrification: Electrification complete, doubling in progress (Earthworks ongoing, track laying not started yet)
3....
more...
1. Ramnagaram-Mysuru doubling and electrification: Doubling of 1.5km stretch at Srirangapatna pending due to shifting of Tipu's armory, it was completed few days ago, so expect doubling of whole stretch to be completed in 1-2 months, electrification in 3 months
2. Yelahanka-Penukonda doubling and electrification: Electrification complete, doubling in progress (Earthworks ongoing, track laying not started yet)
3....
more...
6 Public Posts - Sat Mar 18, 2017
3 Public Posts - Sun Mar 19, 2017
1 Public Posts - Tue Mar 21, 2017
3 Public Posts - Wed Mar 22, 2017
1 Public Posts - Thu Mar 23, 2017
1 Public Posts - Fri Mar 24, 2017
3 Public Posts - Sun Mar 26, 2017
6 Public Posts - Wed Apr 05, 2017
3 Public Posts - Thu Apr 06, 2017
1 Public Posts - Fri Apr 07, 2017
1 Public Posts - Sat Apr 08, 2017
10 Public Posts - Wed Apr 19, 2017
5 Public Posts - Thu Apr 20, 2017
8 Public Posts - Fri Apr 21, 2017
6 Public Posts - Sat Apr 22, 2017
11 Public Posts - Sun Apr 23, 2017
1 Public Posts - Sun Apr 30, 2017
2 Public Posts - Mon May 01, 2017
3 Public Posts - Tue May 02, 2017
2 Public Posts - Wed May 03, 2017
1 Public Posts - Tue May 16, 2017
1 Public Posts - Tue Jun 27, 2017