Status of Kadapa-Bengaluru railway line and the quantum of funds allocated for this project and
A new line project between Kadapa-Bengaluru (255.40 km) was included in the Railway Budget 2008-09 with an anticipated cost
of 2061 crore. Expenditure incurred upto March,2016 is 183.35crore. Railway has given the outlay of 156.16 crore for 2016-17 and
further outlay of 240 crore has been proposed for...
more...
A new line project between Kadapa-Bengaluru (255.40 km) was included in the Railway Budget 2008-09 with an anticipated cost
of 2061 crore. Expenditure incurred upto March,2016 is 183.35crore. Railway has given the outlay of 156.16 crore for 2016-17 and
further outlay of 240 crore has been proposed for...
more...