Plan ke hisaab se actually JBP-KTE June 2016 me khatam ho jana tha but due to CBI raid the work go to a standstill. Meanwhile ET-PPI got to completion aur KTE-JBP bahut dheeri speed se chalu hua. Abhi bhi target 2017 June h KTE-JBP ka. Someone posted about electrification of MML and that company will electrify till JBP coaching depot. That is because KTE-JBP electrification will be over before PPI-JBP and so, connecting OHE from MML with coaching depot and all the way to KTE.