May 26 2017 (11:41) GR/Kalaburagi Junction (Gulbarga) (4 PFs)
SunilKulkarni~
SunilKulkarni~ 2006 blog postsUpdates on Bidar Gulbarga New line at Sultanpur Station(Outskirts of Gulbarga)
- All platform works completed with FUB..
- LED lights are shining
- Huge Goods shed is almost ready( the existing Gulbarga station Goods shed will be shifted to Sultanpur Station soon)
-...
more...
- All platform works completed with FUB..
- LED lights are shining
- Huge Goods shed is almost ready( the existing Gulbarga station Goods shed will be shifted to Sultanpur Station soon)
-...
more...
2 Public Posts - Fri May 26, 2017
As per latest the Line commissioning dead line is August 2017( next 3-4 months). And pit line at Bidar(Khanapur) all civil works is done already may be they ware waiting for some grand day to open... nearing elections... as few more things need big band opening like Yadgir Railway factory, Bidar-Gulbarga new line, Gulbarga-Wadi electrification, Bidar Pit line, and Gulbarga Railway division (?????)...