** Itarsi - Jabalpur Electrification Detailed Update **
1. Itarsi- Pipariya (67 KMS): Double Electric Line. Electric locos already plying.
2. Pipariya-Salichauka Road (36 KMS):- Poles erected. Clippers installed. Catenary along with contact wire installed. Tightening done. Work at stations done. (Completed)
3. Salichauka Road - Bohani (27 KMS):- Poles erected. Clippers installed. Catenary wire along with contact wire installed, except in few patches....
more...
1. Itarsi- Pipariya (67 KMS): Double Electric Line. Electric locos already plying.
2. Pipariya-Salichauka Road (36 KMS):- Poles erected. Clippers installed. Catenary along with contact wire installed. Tightening done. Work at stations done. (Completed)
3. Salichauka Road - Bohani (27 KMS):- Poles erected. Clippers installed. Catenary wire along with contact wire installed, except in few patches....
more...