Search Forum
Blog Entry# 2933068
Posted: Dec 25 2017 (12:54)
4 Responses
Last Response: Dec 26 2017 (12:16)
4 Responses
Last Response: Dec 26 2017 (12:16)
New Facilities/Technology
SWR/South Western
Syedmuzz~ 133 news posts
Tender is out for the electrification of Hosapete - Hubballi - Tinaighat section of UBL division - SWR.
Ref:...
Ref:...
2 Public Posts - Mon Dec 25, 2017
For package-1-Hospet-Torangallu-kudatini=45km Double line=45*2=90km
& Torangallu-Ranjitpura=22Km Single line
So total for 112Km need 24 Months to Finish RE?
& Torangallu-Ranjitpura=22Km Single line
So total for 112Km need 24 Months to Finish RE?
1 Public Posts - Tue Dec 26, 2017