Oct 14 2018 (15:33) 16592/Hampi Express | HPT/Hosapete Junction (Hospet) (3 PFs)
DeepakUlli~
DeepakUlli~ 2929 blog postsHosapete- guntakal double electrification work update:as on 13/10/2018
*guntakal - hagari =electrification work successfully completed
* hargari - ballari city out limits (gtl side) only erected electrical poles are installed wiring not done
* ballari city outer limits(gtl side ) - kudutani only OHE PIT HOLES WORK GOING ON.
*...
more...
*guntakal - hagari =electrification work successfully completed
* hargari - ballari city out limits (gtl side) only erected electrical poles are installed wiring not done
* ballari city outer limits(gtl side ) - kudutani only OHE PIT HOLES WORK GOING ON.
*...
more...
37 Posts
Thanks. Any idea what is the target date for commissioning of GTL ELS?
No ..information about that ..if want u can ask Vishnu in gtl group he is right person ..he know most of things about gtl and surrounding..
When i enquired a rf from gtl in you tube he replied that almost outer works of gtl els is completed track laying and linking to the main line is pending and also inner work must be done it will take another two years for gtl els to be fully operational.