Central Railway block for 1 month in Daund - Kurudwadi section. For Doubling work between Bhigwan & Wadshinge Central Railway has decided 2 hours 15 mins block daily between Daund & Kurudwadi.
12169/70 Pune - Solapur Intercity (Indrayani) Exp cancelled from 3 Dec 2018 - 1 Jan 2019.
12169/70 Pune - Solapur Intercity (Indrayani) Exp cancelled from 3 Dec 2018 - 1 Jan 2019.
5 Posts
Railway is planning to use existing bridges for new doubling line....
If you observe you can see existing track allognment is on the one side of the bridge.
Also a project reposrt also says existing bridge to be used...
So no new construction of bridges...
Also a project reposrt also says existing bridge to be used...
So no new construction of bridges...
Thanks for this information but one think yard remodeling take at lease 6 month so wadhshinge Bhalwani open in December 2019 late or 2020
What is current status on doubling and when CRS between wadhshinge Bhalwani
This year there is no CRS inspection solapur railway division
This year there is no CRS inspection solapur railway division