Dec 05 2018 (23:48) 14241/Nauchandi Express | ALD/Allahabad (10 PFs)
highvoltageeee2k3~
highvoltageeee2k3~ 447 blog postsquestion guys, what are the doubling projects currently being executed in uttar pradesh.
LKO-FD-JNU is 60 percent doubled...
LKO-PBH-JNH is 80 percent doubled...
JNH-BSB doubling now done..
ALD-ALY-MUV-BSB only ground levelling done..
CNB-JHS 60-70 percent done..
ALD-PFM...
more...
LKO-PBH-JNH is 80 percent doubled...
JNH-BSB doubling now done..
ALD-ALY-MUV-BSB only ground levelling done..
CNB-JHS 60-70 percent done..
ALD-PFM...
more...
Hi thanks,
Of these which ones are critical to decongest the routes?
Of these which ones are critical to decongest the routes?
भाई...वैसे... तो Google Rail Map / Atlas पे तो दिखा नहीं रहा है तो... डबलिंग वर्क कैसे प्रारम्भ होगा...!!!
Railway budget me to aa Gaya hai I think Abhi fund nahi Mila hoga isilye Jese fund milega ye bhi 3-4 saal me complete ho jayega