Electrification Update, Mavli Junction to Udaipur.
1. Electrification outside Mavli. The traction substation is fully set up (expect pics later this week!) and the junction itself is well wired.
2. Sectioning post just before Bhimal.
3....
more...
1. Electrification outside Mavli. The traction substation is fully set up (expect pics later this week!) and the junction itself is well wired.
2. Sectioning post just before Bhimal.
3....
more...
5 Public Posts - Sat Dec 22, 2018
Jis din complete wire aur pole lag jayge na uske baad b 2 month tk finishing ka kaam chaltha h abhi tk itne crs hue h unme ye baat note ki h aur abhi yaha tk Udaipur railway station pe kaam b start nhi hua h