I know that CRS for electrified double line is happening in Makalidurga - Devarapalli section today & tomorrow. But rajasmrao sir asked about Yelahanka - Doddaballapur doubling. So I said that I don't know regarding this section
only land leveling done in this section. Will take atleast 4-6 more months to complete doubling here.
thanks a ton for the information, question after YNK dodbollapur what stretch is going for commissioning?
before YNK-DBU, DBU-MKL will be commissioned in the next few months.
DBU MKL track works aren't started yet . Infact Oddarahalli both sides to and fro SBC Land levelling needs to be done few meters outer from station side . YNK DBU some progress has been done from DBU - RNN ,most likely they might take up that stretch after commissioning of MKL DPE. Reason being to run MEMU suburban services upto DBU from YPR YNK DBU