The detailed electrification tracker for the FY 2019-20 uploaded here.
The sections in green are outside of the list provided by CORE.
The images show detailed section-wise with CRS Inspection and loco trial date.
Please let me know if I have missed any section.
Source:...
more...
The sections in green are outside of the list provided by CORE.
The images show detailed section-wise with CRS Inspection and loco trial date.
Please let me know if I have missed any section.
Source:...
more...
211 Posts
Rayadurgam - Talaku CRS inspection was done yesterday i.e., 30/06/2020
Thanks,
Meanwhile, e loco trial for Bhandarkund-Bhimalgondi section, last of NGP CWA of SECR was also done today.
Meanwhile, e loco trial for Bhandarkund-Bhimalgondi section, last of NGP CWA of SECR was also done today.