Nov 26 2019 (23:19) 19943/Udaipur - Ahmedabad MG Express (UnReserved) | KRCD/Kharwa Chanda (2 PFs)guest
Tunnel Work under progress in Kharwa - Zawar section
Total length of 840 meters. (Probably Southern Rajasthan's longest rail tunnel and 2nd largest in all tunnels of Rajasthan)
more than 270 mts. have already been dug.
Estimated time to complete: Dec. 2020
PC-...
more...
Total length of 840 meters. (Probably Southern Rajasthan's longest rail tunnel and 2nd largest in all tunnels of Rajasthan)
more than 270 mts. have already been dug.
Estimated time to complete: Dec. 2020
PC-...
more...