Feb 26 2020 (11:04) 22157/Mumbai CSMT - Chennai Egmore SF Mail (PT) | DUD/Dudhani (3 PFs)
psanga_sur^~
psanga_sur^~ 5601 blog posts#PuneSolapurGulbargaDoubling
Boroti to Kulali 23 Kms doubling commissioned yesterday which is the part of Solapur - Gulbarga doubling. Now only 27 Kms of doubling work between Kulali and Sawalagi is remaining which is expected to complete by Dec 2020.
IR conducted trial yesterday with 120 Km/hr speed. Kalyan WDM-3D Twins was used for this.
Traffic is started on the second line...
more...
Boroti to Kulali 23 Kms doubling commissioned yesterday which is the part of Solapur - Gulbarga doubling. Now only 27 Kms of doubling work between Kulali and Sawalagi is remaining which is expected to complete by Dec 2020.
IR conducted trial yesterday with 120 Km/hr speed. Kalyan WDM-3D Twins was used for this.
Traffic is started on the second line...
more...
16 Posts
It is in progress.
Bhalawani to kurduwadi outer is completed.
Also entire Miraj - Kurduwadi outer section wiring is completed.
Bhalawani to kurduwadi outer is completed.
Also entire Miraj - Kurduwadi outer section wiring is completed.
Hi bro,by when can we expect the entire Mumbai-Chennai line to be doubly electrified?
With the corona outbreak now and lockdown implemented,it might be delayed right?