OHE Poles without Wiring are Installed in this station for Hotgi Gadag Electrification project..
5 Posts
Work was started in July now till honaganahalli poles are erected and wiring is also completed for many stretch so its not a problem to meet the target
Any update about doubling between Wandal Gadag section? Last time I heard doubling works taking place between Mallapur to Holealur in Gadag Bagalkot section..
Gadag Holehalur doubling will be comissioned by Jan 2021. Holehalur Wandal by dec 2021. Ohe pole erection has started from Gadag side towards Hotgi