Engine rolling was completed successfully by team #RVNL between Kesinga - Titlagarh,12.96 kms, third line on 30.1.21. Electrification work is also being done here. The section includes a 650 m long important bridge across Tel river in Odisha.
Engine rolling is the first phase in commissioning of the section indicating completion of the block section. CRS inspection takes place after this. 2000 MT structural steel, 2200 MT reinforcement steel,11000 Cu.m concrete and 92000 bags cement were used in this work.
Source:...
more...
Engine rolling is the first phase in commissioning of the section indicating completion of the block section. CRS inspection takes place after this. 2000 MT structural steel, 2200 MT reinforcement steel,11000 Cu.m concrete and 92000 bags cement were used in this work.