झारखंड से उत्तर प्रदेश को जोड़ने वाली रेल लाइन पर जल्द ही ट्रेनों की स्पीड बढ़ेगी। धनबाद रेल मंडल के अधीन रेल मार्ग का दोहरीकरण पूरा...
3 Public Posts - Tue Dec 07, 2021
DXN-MXY left else approx. GHD to JRQ doubled and electrified. BXLL -CPU and PPKD- MWF also done, SGRL-MHDA done just points need to be interlocked. Out of 200km around 50% is done. WCR is also going in great pace , Just forest reserve is bottleneck hence no work started between Beohari to Marwasgram 50 km apart from that almost 80-90% section is done and much probably commissioned by march 2022.