Today RE Works CRS conducted on Rajewadi(incl) to Adarki(incl) section of Pune Miraj Line
#AtlasMonitor Please Update the map
Rajewadi Ambale :- Double Electric Line
Ambale Jejuri Daundaj :- Electric Line-Doubling
Daundaj Valha...
more...
#AtlasMonitor Please Update the map
Rajewadi Ambale :- Double Electric Line
Ambale Jejuri Daundaj :- Electric Line-Doubling
Daundaj Valha...
more...
12 Posts
Doubling work
1. Lonanad to adarki 18 km completed
2. Bhilwadi to kirloskarwadi 14 km completed
...
more...
1. Lonanad to adarki 18 km completed
2. Bhilwadi to kirloskarwadi 14 km completed
...
more...
Electrification work remaining between adarki to satara only rest work completed
As the single line Electrification is completed from Pune to Miraj. When can v expect E locos for Koyna, Mahalaxmi exp and many others?